 |  |  | | Calendar | Timeline for May 2022 PIPP RFP | Activity | Date | Pre-Procurement Activity | | Bidder Information Session | Thursday, March 10, 2022 | PIPP Supplier Application can be submitted | Friday, March 11, 2022 | Announcement regarding the blended SSO price | Wednesday, April 20, 2022 | PIPP Supplier Application is due | Thursday, April 21, 2022 | Notifications to Registered Bidders | Tuesday, April 26, 2022 | May 2, 2022 RFP | | Pre-Bid security due | Thursday, April 28, 2022 | Bid window to submit bids (10:00 AM to 02:00 PM ET) | Monday, May 2, 2022 | CRA notifies Companies and PUCO of results (tentative) | Monday, May 2, 2022 | PUCO acceptance of results (tentative) | Wednesday, May 4, 2022 | Master PIPP Supply Agreement signed (tentative) | Friday, May 6, 2022 | Power flow | Wednesday, June 1, 2022 | 2022 Supplemental RFP (if necessary) | | Pre-Bid security due | Thursday, May 12, 2022 | Bid window to submit bids (10:00 AM to 02:00 PM ET) | Monday, May 16, 2022 | CRA notifies the Companies and PUCO of results (tentative) | Monday, May 16, 2022 | PUCO acceptance of results (tentative) | Wednesday, May 18, 2022 | Master PIPP Supply Agreement signed (tentative) | Friday, May 20, 2022 | Power flow | Wednesday, June 1, 2022 | | |  |  |  |
|