Timeline for April 2025 PIPP RFP
Activity Date
Pre-Procurement Activity
Bidder Information Session Tuesday, March 11, 2025
PIPP Supplier Application can be submitted Tuesday, March 11, 2025
PIPP Supplier Application is due Wednesday, April 2, 2025
Notifications to Registered Bidders Wednesday, April 2, 2025
Announcement regarding the blended SSO price Thursday, April 3, 2025
April 14, 2025 RFP
Pre-Bid security due Tuesday, April 8, 2025
Bid window to submit bids (10:00 AM to 02:00 PM ET) Monday, April 14, 2025
CRA notifies AES Ohio and PUCO of results (tentative) Monday, April 14, 2025
PUCO acceptance of results (tentative) Wednesday, April 16, 2025
Master PIPP Supply Agreement signed (tentative) Friday, April 18, 2025
Power flow Sunday, June 1, 2025
2025 Supplemental RFP (if necessary)
Pre-Bid security due Friday, April 25, 2025
Bid window to submit bids (10:00 AM to 02:00 PM ET) Tuesday, April 29, 2025
CRA notifies AES Ohio and PUCO of results (tentative) Tuesday, April 29, 2025
PUCO acceptance of results (tentative) Wednesday, April 30, 2025
Master PIPP Supply Agreement signed (tentative) Friday, May 2, 2025
Power flow Sunday, June 1, 2025